Doe Project


Project Start Date: Wed 6/4/97
Project Finish Date: Mon 6/15/98

Tasks with Assignments

IDTask NameWorkDurationStartFinish% Work Complete
1Contracts0 hrs0 daysMon 6/15/98Mon 6/15/980%
2__Supply Lot Sale Agreement0 hrs0 daysMon 6/15/98Mon 6/15/980%
3__Supply Construction Agreement0 hrs0 daysWed 6/4/97Wed 6/4/970%
4__Supply Contract Plans0 hrs1 dayWed 6/4/97Wed 6/4/970%
5__Supply Contract Specifications0 hrs1 dayWed 6/4/97Wed 6/4/970%
6__Supply Contract Site Plan0 hrs1 dayWed 6/4/97Wed 6/4/970%
7__Secure Financing0 hrs0 daysMon 6/15/98Mon 6/15/980%
8__Construction Loan Settlement0 hrs0 daysMon 6/15/98Mon 6/15/980%
9Document Review & Revision0 hrs25 daysMon 6/15/98Wed 7/1/980%
10__Review & Finalize Plans0 hrs1 dayWed 6/4/97Wed 6/4/970%
11__Review & Finalize Specifications0 hrs1 dayWed 6/4/97Wed 6/4/970%
12__Review & Finalize Site Plan0 hrs1 dayWed 6/25/97Wed 6/25/970%
13__Print Construction Drawings0 hrs1 dayWed 7/2/97Wed 7/2/970%
14__Approve Revised Plans0 hrs1 dayTue 7/8/97Tue 7/8/970%
15__Approve Revised Specifications0 hrs1 dayTue 7/8/97Tue 7/8/970%
16__Approve Revised Site Plan0 hrs1 dayTue 7/8/97Tue 7/8/970%
17Bids & Contracts0 hrs24 daysMon 6/15/98Tue 6/30/980%
18__Make Copies of Plans0 hrs1 dayWed 7/9/97Wed 7/9/970%
19__Make Copies of Specifications0 hrs1 dayWed 7/9/97Wed 7/9/970%
20__Distribute Plans & Specifications0 hrs1 dayMon 7/14/97Mon 7/14/970%
21__Receive Bids0 hrs1 dayTue 7/15/97Tue 7/15/970%
22__Review Bids0 hrs5 daysMon 6/15/98Wed 6/17/980%
23 0 hrs1 dayTue 8/5/97Tue 8/5/970%
24 0 hrs1 dayMon 6/15/98Mon 6/15/980%
25__Execute Subcontractor Agreements0 hrs1 dayTue 8/5/97Tue 8/5/970%
26Grading & Building Permits0 hrs17 daysMon 6/15/98Thu 6/25/980%
27__Schedule lot stake-out0 hrs1 dayWed 7/9/97Wed 7/9/970%
28__Stake lot0 hrs1 dayTue 7/15/97Tue 7/15/970%
29__File Grading Permit Application0 hrs1 dayWed 7/9/97Wed 7/9/970%
30__File Building Permit Application0 hrs3 daysTue 7/8/97Wed 7/9/970%
31__Post Lot Identification0 hrs1 dayWed 7/16/97Wed 7/16/970%
32__Meet Sed. Control Insp.0 hrs1 dayThu 7/17/97Thu 7/17/970%
33__Walk Lot w/ Owner0 hrs1 dayFri 7/18/97Fri 7/18/970%
34__Install Construction Entrance0 hrs1 dayMon 7/21/97Mon 7/21/970%
35__Install Sediment Controls0 hrs2 daysMon 7/21/97Mon 7/21/970%
36__Sediment Control Insp.0 hrs1 dayWed 7/23/97Wed 7/23/970%
37__Grading Permit Issued0 hrs1 dayThu 7/24/97Thu 7/24/970%
38__County Permit Process0 hrs1 dayMon 7/14/97Mon 7/14/970%
39__Building Permit Approved0 hrs1 dayMon 7/28/97Mon 7/28/970%
40__Pay Permit Fees and Excise Taxes0 hrs1 dayThu 7/31/97Thu 7/31/970%
41__Building Permit Issued0 hrs0 daysFri 8/1/97Fri 8/1/970%
42Site Work0 hrs7 daysMon 6/15/98Thu 6/18/980%
43__Clear Lot0 hrs3 daysThu 7/24/97Fri 7/25/970%
44__Strip Topsoil & Stockpile0 hrs1 dayWed 7/30/97Wed 7/30/970%
45__Stake Lot for Excavation0 hrs1 dayMon 7/28/97Mon 7/28/970%
46__Rough grade lot0 hrs1 dayMon 7/28/97Mon 7/28/970%
47__Excavate for foundation0 hrs2 daysTue 7/29/97Tue 7/29/970%
48Foundation0 hrs24 daysMon 6/15/98Tue 6/30/980%
49__Layout footings0 hrs1 dayWed 7/30/97Wed 7/30/970%
50__Dig Footings & Install Reinforcing0 hrs1 dayWed 7/30/97Wed 7/30/970%
51__Footing Inspection0 hrs0 daysThu 7/31/97Thu 7/31/970%
52__Pour footings0 hrs1 dayThu 7/31/97Thu 7/31/970%
53__Pin Footings0 hrs1 dayThu 7/31/97Thu 7/31/970%
54__Stock Block, Mortar, Sand0 hrs1 dayFri 8/1/97Fri 8/1/970%
55__Build Block Foundation0 hrs15 daysFri 8/1/97Tue 8/12/970%
56__Foundation Certification0 hrs0 daysTue 9/2/97Tue 9/2/970%
57__Draw #1 (Location Survey)0 hrs0 daysTue 9/2/97Tue 9/2/970%
58__Fill Block Cores w/ Concrete0 hrs1 dayTue 9/2/97Tue 9/2/970%
59__Steel Delivery0 hrs1 dayWed 9/3/97Wed 9/3/970%
60__Set Lintels, Bolts, Cap Block0 hrs2 daysThu 9/4/97Thu 9/4/970%
61__Lumber Delivery0 hrs1 dayWed 9/3/97Wed 9/3/970%
62__Waterproofing and Drain Tile0 hrs1 dayThu 9/4/97Thu 9/4/970%
63Rough Carpentry0 hrs44 daysMon 6/15/98Tue 7/14/980%
64__Set Steel0 hrs1 dayFri 9/5/97Fri 9/5/970%
65__1st Floor Deck Framing0 hrs4 daysMon 9/8/97Tue 9/9/970%
66__1st Floor Wall Framing0 hrs4 daysThu 9/11/97Fri 9/12/970%
67__Draw #2 (First Floor Deck)0 hrs0 daysMon 9/15/97Mon 9/15/970%
68__2nd Floor Deck Framing0 hrs2 daysMon 9/15/97Mon 9/15/970%
69__Draw #3 (Second Floor Deck)0 hrs0 daysTue 9/16/97Tue 9/16/970%
70__2nd Floor Wall Framing0 hrs3 daysTue 9/16/97Wed 9/17/970%
71__Set Roof Trusses0 hrs2 daysWed 9/17/97Thu 9/18/970%
72__Frame Roof0 hrs7 daysThu 9/18/97Tue 9/23/970%
73__Install Roof Plywood0 hrs5 daysWed 9/24/97Fri 9/26/970%
74__Install Windows & Doors0 hrs2 daysTue 9/30/97Tue 9/30/970%
75__Frame Basement0 hrs3 daysWed 10/8/97Thu 10/9/970%
76__Frame Basement Bulkheads0 hrs2 daysWed 11/5/97Wed 11/5/970%
77Concrete Slabs0 hrs8 daysMon 6/15/98Thu 6/18/980%
78__Basement Slab Preparation0 hrs2 daysWed 9/17/97Wed 9/17/970%
79__Termite Treatment Basment Slab0 hrs1 dayFri 9/19/97Fri 9/19/970%
80__Slab Inspection0 hrs1 dayMon 9/22/97Mon 9/22/970%
81__Pour Basement Slab0 hrs1 dayTue 9/23/97Tue 9/23/970%
82__Prep Garage Slab0 hrs1 dayWed 9/24/97Wed 9/24/970%
83__Termite Treatment Garage Slab0 hrs1 dayThu 9/25/97Thu 9/25/970%
84__Pour Garage Slab0 hrs1 dayFri 9/26/97Fri 9/26/970%
85H.V.A.C.0 hrs17 daysMon 6/15/98Thu 6/25/980%
86__HVAC Layout & Measure0 hrs1 dayThu 10/9/97Thu 10/9/970%
87__HVAC Rough-in0 hrs5 daysFri 10/17/97Tue 10/21/970%
88__HVAC Set Indoor Units0 hrs2 daysTue 10/28/97Tue 10/28/970%
89__HVAC Temporary Heat0 hrs2 daysThu 10/30/97Thu 10/30/970%
90Plumbing Rough-in0 hrs37 daysMon 6/15/98Thu 7/9/980%
91__Plumbing Sub-slab0 hrs2 daysMon 9/15/97Mon 9/15/970%
92__Plumbing Layout0 hrs1 dayMon 10/27/97Mon 10/27/970%
93__Plumbing rough-in0 hrs5 daysMon 10/27/97Wed 10/29/970%
94County Plumbing Sub-slab Inspection0 hrs0 daysWed 9/17/97Wed 9/17/970%
95County Plumbing Rough-in Inspection0 hrs0 daysWed 11/5/97Wed 11/5/970%
96Electric Rough-in0 hrs19 daysWed 11/12/97Tue 11/25/970%
97__Set Electric Boxes0 hrs2 daysFri 10/17/97Mon 10/20/970%
98__Install Electric Service Panel0 hrs2 daysMon 10/20/97Tue 10/21/970%
99__Electrical Walk-through0 hrs1 dayTue 10/21/97Tue 10/21/970%
100__Electrical Rough-wire0 hrs14 daysWed 10/22/97Thu 10/30/970%
101Specialty Rough-ins0 hrs5 daysFri 11/21/97Tue 11/25/970%
102__Central Vacuum Rough-in0 hrs5 daysMon 11/17/97Wed 11/19/970%
103__Alarm System Rough-in0 hrs5 daysMon 11/17/97Wed 11/19/970%
104__Telephone System Rough-in0 hrs5 daysMon 11/17/97Wed 11/19/970%
105__Television System Rough-in0 hrs5 daysMon 11/17/97Wed 11/19/970%
106__Audio Visual Rough-in0 hrs5 daysMon 11/17/97Wed 11/19/970%
107County Electrical inspection0 hrs0 daysWed 11/26/97Wed 11/26/970%
108Draw #5 (Rough-ins complete)0 hrs0 daysWed 11/26/97Wed 11/26/970%
109County Framing Inspection0 hrs0 daysWed 11/26/97Wed 11/26/970%
110Roofing0 hrs68 daysMon 6/15/98Thu 7/30/980%
111__Roofing Paper Installed0 hrs3 daysFri 9/26/97Mon 9/29/970%
112__Draw #4 (Roof, windows, doors)0 hrs0 daysThu 10/23/97Thu 10/23/970%
113__Stock Roof Shingles0 hrs1 dayThu 10/23/97Thu 10/23/970%
114__Install Roof Shingles0 hrs7 daysTue 1/6/98Fri 1/9/980%
115Exterior Finishes0 hrs56 daysMon 6/15/98Wed 7/22/980%
116__Siding0 hrs3 daysWed 10/1/97Thu 10/2/970%
117__Exterior Trim0 hrs7 daysThu 10/2/97Tue 10/7/970%
118__Brick Arch Forms0 hrs1 dayWed 10/8/97Wed 10/8/970%
119__Brick Veneer0 hrs45 daysWed 10/8/97Fri 11/7/970%
120Insulation0 hrs5 daysWed 11/26/97Fri 11/28/970%
121__Caulk & Air Seal0 hrs1 dayWed 11/26/97Wed 11/26/970%
122__Draft & Fire Stop0 hrs1 dayThu 11/27/97Thu 11/27/970%
123__Batt Insulation0 hrs3 daysThu 11/27/97Fri 11/28/970%
124County Insulation Inspection0 hrs0 daysMon 12/1/97Mon 12/1/970%
125BGE Energy Wise Inspection0 hrs0 daysThu 12/4/97Thu 12/4/970%
126Drywall0 hrs26 daysTue 12/23/97Thu 1/8/980%
127__Stock Drywall0 hrs1 dayMon 12/1/97Mon 12/1/970%
128__Hang Drywall0 hrs5 daysMon 12/1/97Wed 12/3/970%
129__Remove Scrap Drywall0 hrs1 dayThu 12/4/97Thu 12/4/970%
130__Tape and Finish Drywall0 hrs15 daysThu 12/4/97Mon 12/15/970%
131__Sand Drywall0 hrs1 dayTue 12/30/97Tue 12/30/970%
132__Drywall Point-up0 hrs3 daysMon 1/5/98Tue 1/6/980%
133Draw #6 (Insulation & drywall applied)0 hrs0 daysFri 1/9/98Fri 1/9/980%
134Floor Finishes0 hrs76 daysMon 6/15/98Wed 8/5/980%
135__Ceramic Tile0 hrs15 daysThu 1/1/98Mon 1/12/980%
136__Install Hardwood Floor0 hrs4 daysWed 3/25/98Thu 3/26/980%
137__Sand, Stain, Seal Hardwood0 hrs5 daysMon 4/13/98Wed 4/15/980%
138__Install Carpet0 hrs4 daysTue 4/21/98Wed 4/22/980%
139__Final Coat Hardwood0 hrs2 daysWed 4/15/98Wed 4/15/980%
140Paint0 hrs59 daysTue 2/17/98Mon 3/30/980%
141__Prep Drywall for Prime Coat0 hrs2 daysTue 12/30/97Wed 12/31/970%
142__Prime Paint Drywall0 hrs2 daysWed 12/31/97Thu 1/1/980%
143__Prep Trim for Prime Coat0 hrs2 daysTue 1/20/98Tue 1/20/980%
144__Prime Trim0 hrs2 daysThu 1/22/98Thu 1/22/980%
145__Finish Coat Trim0 hrs10 daysMon 2/16/98Fri 2/20/980%
146__Finish Coat Drywall0 hrs14 daysThu 2/26/98Fri 3/6/980%
147__Caulk Exterior Windows & Doors0 hrs1 dayThu 3/26/98Thu 3/26/980%
148__Finish Coat Exterior Trim & Siding0 hrs1 dayFri 3/27/98Fri 3/27/980%
149Draw #7 (Roofing, masonry, siding)0 hrs0 daysTue 3/31/98Tue 3/31/980%
150Interior Trim0 hrs29 daysMon 6/15/98Fri 7/3/980%
151__Interior Trim Delivery0 hrs1 dayTue 1/6/98Tue 1/6/980%
152__Install Interior Doors0 hrs5 daysWed 1/7/98Fri 1/9/980%
153__Install Interior Trim0 hrs15 daysFri 1/9/98Tue 1/20/980%
154__Install Cabinetry0 hrs5 daysFri 2/6/98Tue 2/10/980%
155__Install Appliances0 hrs1 dayThu 2/12/98Thu 2/12/980%
156__1st Punch-out Interior Trim0 hrs2 daysFri 2/13/98Fri 2/13/980%
157H.V.A.C. Trim0 hrs1 dayMon 3/30/98Mon 3/30/980%
158__Install Grills & Registers for Paint0 hrs1 dayMon 3/30/98Mon 3/30/980%
159__Set Outdoor Units0 hrs1 dayMon 3/30/98Mon 3/30/980%
160Plumbing Trim0 hrs5 daysFri 4/3/98Tue 4/7/980%
161__Set Fixtures0 hrs4 daysTue 3/31/98Wed 4/1/980%
162__Connect Appliances0 hrs1 dayTue 4/7/98Tue 4/7/980%
163County Final Plumbing Inspection0 hrs0 daysWed 4/8/98Wed 4/8/980%
164Exterior Landscaping0 hrs32 daysMon 6/15/98Mon 7/6/980%
165__Rough Final Grade0 hrs1 dayWed 1/7/98Wed 1/7/980%
166__Patios0 hrs7 daysWed 1/7/98Mon 1/12/980%
167__Porches0 hrs5 daysMon 1/19/98Wed 1/21/980%
168__Sidewalks0 hrs7 daysFri 1/23/98Wed 1/28/980%
169__Decks0 hrs7 daysTue 2/3/98Fri 2/6/980%
170__Driveways0 hrs2 daysTue 2/17/98Tue 2/17/980%
171__Final Grade and Seed0 hrs3 daysWed 2/18/98Thu 2/19/980%
172Electrical Final Trim0 hrs160 daysMon 6/15/98Fri 10/2/980%
173__Switch & Plug0 hrs2 daysMon 1/12/98Mon 1/12/980%
174__Install Fixtures0 hrs1 dayMon 6/15/98Mon 6/15/980%
175__Connect Appliances0 hrs1 dayMon 6/15/98Mon 6/15/980%
176Hardware0 hrs12 daysFri 4/3/98Fri 4/10/980%
177__Door Hardware0 hrs2 daysThu 3/26/98Thu 3/26/980%
178__Bath Hardware0 hrs2 daysMon 3/23/98Mon 3/23/980%
179__Mirrors0 hrs5 daysThu 3/26/98Mon 3/30/980%
180__Shower Doors0 hrs10 daysTue 3/24/98Mon 3/30/980%
181Draw #8 (Prime paint, cabinets, doors)0 hrs0 daysTue 2/17/98Tue 2/17/980%
182Draw #9 (Trim, furnace, hrdwd, tile, rails)0 hrs0 daysTue 2/17/98Tue 2/17/980%
183Draw #10 (Plumbing & elec. trim, final paint)0 hrs0 daysThu 3/26/98Thu 3/26/980%
184Final Building Inspection0 hrs0 daysThu 3/26/98Thu 3/26/980%
185Use & Occupancy Certificate0 hrs0 daysMon 3/30/98Mon 3/30/980%
186First Walk-thru0 hrs0 daysMon 3/30/98Mon 3/30/980%
187Draw #11 (Final payment per contract)0 hrs0 daysTue 3/31/98Tue 3/31/980%
188Final Punch-out0 hrs9 daysMon 4/6/98Fri 4/10/980%
189__Punch Out Walk-thru List0 hrs4 daysMon 3/30/98Tue 3/31/980%
190__Trim and Adjust Doors0 hrs2 daysMon 4/6/98Mon 4/6/980%
191__Paint Touch-up0 hrs3 daysTue 4/7/98Wed 4/8/980%
192Cleaning0 hrs14 daysThu 4/2/98Mon 4/13/980%
193__Windows0 hrs3 daysWed 3/25/98Thu 3/26/980%
194__Rough Clean0 hrs3 daysMon 3/30/98Tue 3/31/980%
195__Final Clean0 hrs2 daysMon 4/13/98Mon 4/13/980%
196Final Walk-through0 hrs0 daysMon 4/13/98Mon 4/13/980%
197Move-in0 hrs0 daysThu 4/16/98Thu 4/16/980%