| ID | Task Name | Work | Duration | Start | Finish | % Work Complete |
| 1 | Contracts | 0 hrs | 0 days | Mon 6/15/98 | Mon 6/15/98 | 0% |
| 2 | __Supply Lot Sale Agreement | 0 hrs | 0 days | Mon 6/15/98 | Mon 6/15/98 | 0% |
| 3 | __Supply Construction Agreement | 0 hrs | 0 days | Wed 6/4/97 | Wed 6/4/97 | 0% |
| 4 | __Supply Contract Plans | 0 hrs | 1 day | Wed 6/4/97 | Wed 6/4/97 | 0% |
| 5 | __Supply Contract Specifications | 0 hrs | 1 day | Wed 6/4/97 | Wed 6/4/97 | 0% |
| 6 | __Supply Contract Site Plan | 0 hrs | 1 day | Wed 6/4/97 | Wed 6/4/97 | 0% |
| 7 | __Secure Financing | 0 hrs | 0 days | Mon 6/15/98 | Mon 6/15/98 | 0% |
| 8 | __Construction Loan Settlement | 0 hrs | 0 days | Mon 6/15/98 | Mon 6/15/98 | 0% |
| 9 | Document Review & Revision | 0 hrs | 25 days | Mon 6/15/98 | Wed 7/1/98 | 0% |
| 10 | __Review & Finalize Plans | 0 hrs | 1 day | Wed 6/4/97 | Wed 6/4/97 | 0% |
| 11 | __Review & Finalize Specifications | 0 hrs | 1 day | Wed 6/4/97 | Wed 6/4/97 | 0% |
| 12 | __Review & Finalize Site Plan | 0 hrs | 1 day | Wed 6/25/97 | Wed 6/25/97 | 0% |
| 13 | __Print Construction Drawings | 0 hrs | 1 day | Wed 7/2/97 | Wed 7/2/97 | 0% |
| 14 | __Approve Revised Plans | 0 hrs | 1 day | Tue 7/8/97 | Tue 7/8/97 | 0% |
| 15 | __Approve Revised Specifications | 0 hrs | 1 day | Tue 7/8/97 | Tue 7/8/97 | 0% |
| 16 | __Approve Revised Site Plan | 0 hrs | 1 day | Tue 7/8/97 | Tue 7/8/97 | 0% |
| 17 | Bids & Contracts | 0 hrs | 24 days | Mon 6/15/98 | Tue 6/30/98 | 0% |
| 18 | __Make Copies of Plans | 0 hrs | 1 day | Wed 7/9/97 | Wed 7/9/97 | 0% |
| 19 | __Make Copies of Specifications | 0 hrs | 1 day | Wed 7/9/97 | Wed 7/9/97 | 0% |
| 20 | __Distribute Plans & Specifications | 0 hrs | 1 day | Mon 7/14/97 | Mon 7/14/97 | 0% |
| 21 | __Receive Bids | 0 hrs | 1 day | Tue 7/15/97 | Tue 7/15/97 | 0% |
| 22 | __Review Bids | 0 hrs | 5 days | Mon 6/15/98 | Wed 6/17/98 | 0% |
| 23 | | 0 hrs | 1 day | Tue 8/5/97 | Tue 8/5/97 | 0% |
| 24 | | 0 hrs | 1 day | Mon 6/15/98 | Mon 6/15/98 | 0% |
| 25 | __Execute Subcontractor Agreements | 0 hrs | 1 day | Tue 8/5/97 | Tue 8/5/97 | 0% |
| 26 | Grading & Building Permits | 0 hrs | 17 days | Mon 6/15/98 | Thu 6/25/98 | 0% |
| 27 | __Schedule lot stake-out | 0 hrs | 1 day | Wed 7/9/97 | Wed 7/9/97 | 0% |
| 28 | __Stake lot | 0 hrs | 1 day | Tue 7/15/97 | Tue 7/15/97 | 0% |
| 29 | __File Grading Permit Application | 0 hrs | 1 day | Wed 7/9/97 | Wed 7/9/97 | 0% |
| 30 | __File Building Permit Application | 0 hrs | 3 days | Tue 7/8/97 | Wed 7/9/97 | 0% |
| 31 | __Post Lot Identification | 0 hrs | 1 day | Wed 7/16/97 | Wed 7/16/97 | 0% |
| 32 | __Meet Sed. Control Insp. | 0 hrs | 1 day | Thu 7/17/97 | Thu 7/17/97 | 0% |
| 33 | __Walk Lot w/ Owner | 0 hrs | 1 day | Fri 7/18/97 | Fri 7/18/97 | 0% |
| 34 | __Install Construction Entrance | 0 hrs | 1 day | Mon 7/21/97 | Mon 7/21/97 | 0% |
| 35 | __Install Sediment Controls | 0 hrs | 2 days | Mon 7/21/97 | Mon 7/21/97 | 0% |
| 36 | __Sediment Control Insp. | 0 hrs | 1 day | Wed 7/23/97 | Wed 7/23/97 | 0% |
| 37 | __Grading Permit Issued | 0 hrs | 1 day | Thu 7/24/97 | Thu 7/24/97 | 0% |
| 38 | __County Permit Process | 0 hrs | 1 day | Mon 7/14/97 | Mon 7/14/97 | 0% |
| 39 | __Building Permit Approved | 0 hrs | 1 day | Mon 7/28/97 | Mon 7/28/97 | 0% |
| 40 | __Pay Permit Fees and Excise Taxes | 0 hrs | 1 day | Thu 7/31/97 | Thu 7/31/97 | 0% |
| 41 | __Building Permit Issued | 0 hrs | 0 days | Fri 8/1/97 | Fri 8/1/97 | 0% |
| 42 | Site Work | 0 hrs | 7 days | Mon 6/15/98 | Thu 6/18/98 | 0% |
| 43 | __Clear Lot | 0 hrs | 3 days | Thu 7/24/97 | Fri 7/25/97 | 0% |
| 44 | __Strip Topsoil & Stockpile | 0 hrs | 1 day | Wed 7/30/97 | Wed 7/30/97 | 0% |
| 45 | __Stake Lot for Excavation | 0 hrs | 1 day | Mon 7/28/97 | Mon 7/28/97 | 0% |
| 46 | __Rough grade lot | 0 hrs | 1 day | Mon 7/28/97 | Mon 7/28/97 | 0% |
| 47 | __Excavate for foundation | 0 hrs | 2 days | Tue 7/29/97 | Tue 7/29/97 | 0% |
| 48 | Foundation | 0 hrs | 24 days | Mon 6/15/98 | Tue 6/30/98 | 0% |
| 49 | __Layout footings | 0 hrs | 1 day | Wed 7/30/97 | Wed 7/30/97 | 0% |
| 50 | __Dig Footings & Install Reinforcing | 0 hrs | 1 day | Wed 7/30/97 | Wed 7/30/97 | 0% |
| 51 | __Footing Inspection | 0 hrs | 0 days | Thu 7/31/97 | Thu 7/31/97 | 0% |
| 52 | __Pour footings | 0 hrs | 1 day | Thu 7/31/97 | Thu 7/31/97 | 0% |
| 53 | __Pin Footings | 0 hrs | 1 day | Thu 7/31/97 | Thu 7/31/97 | 0% |
| 54 | __Stock Block, Mortar, Sand | 0 hrs | 1 day | Fri 8/1/97 | Fri 8/1/97 | 0% |
| 55 | __Build Block Foundation | 0 hrs | 15 days | Fri 8/1/97 | Tue 8/12/97 | 0% |
| 56 | __Foundation Certification | 0 hrs | 0 days | Tue 9/2/97 | Tue 9/2/97 | 0% |
| 57 | __Draw #1 (Location Survey) | 0 hrs | 0 days | Tue 9/2/97 | Tue 9/2/97 | 0% |
| 58 | __Fill Block Cores w/ Concrete | 0 hrs | 1 day | Tue 9/2/97 | Tue 9/2/97 | 0% |
| 59 | __Steel Delivery | 0 hrs | 1 day | Wed 9/3/97 | Wed 9/3/97 | 0% |
| 60 | __Set Lintels, Bolts, Cap Block | 0 hrs | 2 days | Thu 9/4/97 | Thu 9/4/97 | 0% |
| 61 | __Lumber Delivery | 0 hrs | 1 day | Wed 9/3/97 | Wed 9/3/97 | 0% |
| 62 | __Waterproofing and Drain Tile | 0 hrs | 1 day | Thu 9/4/97 | Thu 9/4/97 | 0% |
| 63 | Rough Carpentry | 0 hrs | 44 days | Mon 6/15/98 | Tue 7/14/98 | 0% |
| 64 | __Set Steel | 0 hrs | 1 day | Fri 9/5/97 | Fri 9/5/97 | 0% |
| 65 | __1st Floor Deck Framing | 0 hrs | 4 days | Mon 9/8/97 | Tue 9/9/97 | 0% |
| 66 | __1st Floor Wall Framing | 0 hrs | 4 days | Thu 9/11/97 | Fri 9/12/97 | 0% |
| 67 | __Draw #2 (First Floor Deck) | 0 hrs | 0 days | Mon 9/15/97 | Mon 9/15/97 | 0% |
| 68 | __2nd Floor Deck Framing | 0 hrs | 2 days | Mon 9/15/97 | Mon 9/15/97 | 0% |
| 69 | __Draw #3 (Second Floor Deck) | 0 hrs | 0 days | Tue 9/16/97 | Tue 9/16/97 | 0% |
| 70 | __2nd Floor Wall Framing | 0 hrs | 3 days | Tue 9/16/97 | Wed 9/17/97 | 0% |
| 71 | __Set Roof Trusses | 0 hrs | 2 days | Wed 9/17/97 | Thu 9/18/97 | 0% |
| 72 | __Frame Roof | 0 hrs | 7 days | Thu 9/18/97 | Tue 9/23/97 | 0% |
| 73 | __Install Roof Plywood | 0 hrs | 5 days | Wed 9/24/97 | Fri 9/26/97 | 0% |
| 74 | __Install Windows & Doors | 0 hrs | 2 days | Tue 9/30/97 | Tue 9/30/97 | 0% |
| 75 | __Frame Basement | 0 hrs | 3 days | Wed 10/8/97 | Thu 10/9/97 | 0% |
| 76 | __Frame Basement Bulkheads | 0 hrs | 2 days | Wed 11/5/97 | Wed 11/5/97 | 0% |
| 77 | Concrete Slabs | 0 hrs | 8 days | Mon 6/15/98 | Thu 6/18/98 | 0% |
| 78 | __Basement Slab Preparation | 0 hrs | 2 days | Wed 9/17/97 | Wed 9/17/97 | 0% |
| 79 | __Termite Treatment Basment Slab | 0 hrs | 1 day | Fri 9/19/97 | Fri 9/19/97 | 0% |
| 80 | __Slab Inspection | 0 hrs | 1 day | Mon 9/22/97 | Mon 9/22/97 | 0% |
| 81 | __Pour Basement Slab | 0 hrs | 1 day | Tue 9/23/97 | Tue 9/23/97 | 0% |
| 82 | __Prep Garage Slab | 0 hrs | 1 day | Wed 9/24/97 | Wed 9/24/97 | 0% |
| 83 | __Termite Treatment Garage Slab | 0 hrs | 1 day | Thu 9/25/97 | Thu 9/25/97 | 0% |
| 84 | __Pour Garage Slab | 0 hrs | 1 day | Fri 9/26/97 | Fri 9/26/97 | 0% |
| 85 | H.V.A.C. | 0 hrs | 17 days | Mon 6/15/98 | Thu 6/25/98 | 0% |
| 86 | __HVAC Layout & Measure | 0 hrs | 1 day | Thu 10/9/97 | Thu 10/9/97 | 0% |
| 87 | __HVAC Rough-in | 0 hrs | 5 days | Fri 10/17/97 | Tue 10/21/97 | 0% |
| 88 | __HVAC Set Indoor Units | 0 hrs | 2 days | Tue 10/28/97 | Tue 10/28/97 | 0% |
| 89 | __HVAC Temporary Heat | 0 hrs | 2 days | Thu 10/30/97 | Thu 10/30/97 | 0% |
| 90 | Plumbing Rough-in | 0 hrs | 37 days | Mon 6/15/98 | Thu 7/9/98 | 0% |
| 91 | __Plumbing Sub-slab | 0 hrs | 2 days | Mon 9/15/97 | Mon 9/15/97 | 0% |
| 92 | __Plumbing Layout | 0 hrs | 1 day | Mon 10/27/97 | Mon 10/27/97 | 0% |
| 93 | __Plumbing rough-in | 0 hrs | 5 days | Mon 10/27/97 | Wed 10/29/97 | 0% |
| 94 | County Plumbing Sub-slab Inspection | 0 hrs | 0 days | Wed 9/17/97 | Wed 9/17/97 | 0% |
| 95 | County Plumbing Rough-in Inspection | 0 hrs | 0 days | Wed 11/5/97 | Wed 11/5/97 | 0% |
| 96 | Electric Rough-in | 0 hrs | 19 days | Wed 11/12/97 | Tue 11/25/97 | 0% |
| 97 | __Set Electric Boxes | 0 hrs | 2 days | Fri 10/17/97 | Mon 10/20/97 | 0% |
| 98 | __Install Electric Service Panel | 0 hrs | 2 days | Mon 10/20/97 | Tue 10/21/97 | 0% |
| 99 | __Electrical Walk-through | 0 hrs | 1 day | Tue 10/21/97 | Tue 10/21/97 | 0% |
| 100 | __Electrical Rough-wire | 0 hrs | 14 days | Wed 10/22/97 | Thu 10/30/97 | 0% |
| 101 | Specialty Rough-ins | 0 hrs | 5 days | Fri 11/21/97 | Tue 11/25/97 | 0% |
| 102 | __Central Vacuum Rough-in | 0 hrs | 5 days | Mon 11/17/97 | Wed 11/19/97 | 0% |
| 103 | __Alarm System Rough-in | 0 hrs | 5 days | Mon 11/17/97 | Wed 11/19/97 | 0% |
| 104 | __Telephone System Rough-in | 0 hrs | 5 days | Mon 11/17/97 | Wed 11/19/97 | 0% |
| 105 | __Television System Rough-in | 0 hrs | 5 days | Mon 11/17/97 | Wed 11/19/97 | 0% |
| 106 | __Audio Visual Rough-in | 0 hrs | 5 days | Mon 11/17/97 | Wed 11/19/97 | 0% |
| 107 | County Electrical inspection | 0 hrs | 0 days | Wed 11/26/97 | Wed 11/26/97 | 0% |
| 108 | Draw #5 (Rough-ins complete) | 0 hrs | 0 days | Wed 11/26/97 | Wed 11/26/97 | 0% |
| 109 | County Framing Inspection | 0 hrs | 0 days | Wed 11/26/97 | Wed 11/26/97 | 0% |
| 110 | Roofing | 0 hrs | 68 days | Mon 6/15/98 | Thu 7/30/98 | 0% |
| 111 | __Roofing Paper Installed | 0 hrs | 3 days | Fri 9/26/97 | Mon 9/29/97 | 0% |
| 112 | __Draw #4 (Roof, windows, doors) | 0 hrs | 0 days | Thu 10/23/97 | Thu 10/23/97 | 0% |
| 113 | __Stock Roof Shingles | 0 hrs | 1 day | Thu 10/23/97 | Thu 10/23/97 | 0% |
| 114 | __Install Roof Shingles | 0 hrs | 7 days | Tue 1/6/98 | Fri 1/9/98 | 0% |
| 115 | Exterior Finishes | 0 hrs | 56 days | Mon 6/15/98 | Wed 7/22/98 | 0% |
| 116 | __Siding | 0 hrs | 3 days | Wed 10/1/97 | Thu 10/2/97 | 0% |
| 117 | __Exterior Trim | 0 hrs | 7 days | Thu 10/2/97 | Tue 10/7/97 | 0% |
| 118 | __Brick Arch Forms | 0 hrs | 1 day | Wed 10/8/97 | Wed 10/8/97 | 0% |
| 119 | __Brick Veneer | 0 hrs | 45 days | Wed 10/8/97 | Fri 11/7/97 | 0% |
| 120 | Insulation | 0 hrs | 5 days | Wed 11/26/97 | Fri 11/28/97 | 0% |
| 121 | __Caulk & Air Seal | 0 hrs | 1 day | Wed 11/26/97 | Wed 11/26/97 | 0% |
| 122 | __Draft & Fire Stop | 0 hrs | 1 day | Thu 11/27/97 | Thu 11/27/97 | 0% |
| 123 | __Batt Insulation | 0 hrs | 3 days | Thu 11/27/97 | Fri 11/28/97 | 0% |
| 124 | County Insulation Inspection | 0 hrs | 0 days | Mon 12/1/97 | Mon 12/1/97 | 0% |
| 125 | BGE Energy Wise Inspection | 0 hrs | 0 days | Thu 12/4/97 | Thu 12/4/97 | 0% |
| 126 | Drywall | 0 hrs | 26 days | Tue 12/23/97 | Thu 1/8/98 | 0% |
| 127 | __Stock Drywall | 0 hrs | 1 day | Mon 12/1/97 | Mon 12/1/97 | 0% |
| 128 | __Hang Drywall | 0 hrs | 5 days | Mon 12/1/97 | Wed 12/3/97 | 0% |
| 129 | __Remove Scrap Drywall | 0 hrs | 1 day | Thu 12/4/97 | Thu 12/4/97 | 0% |
| 130 | __Tape and Finish Drywall | 0 hrs | 15 days | Thu 12/4/97 | Mon 12/15/97 | 0% |
| 131 | __Sand Drywall | 0 hrs | 1 day | Tue 12/30/97 | Tue 12/30/97 | 0% |
| 132 | __Drywall Point-up | 0 hrs | 3 days | Mon 1/5/98 | Tue 1/6/98 | 0% |
| 133 | Draw #6 (Insulation & drywall applied) | 0 hrs | 0 days | Fri 1/9/98 | Fri 1/9/98 | 0% |
| 134 | Floor Finishes | 0 hrs | 76 days | Mon 6/15/98 | Wed 8/5/98 | 0% |
| 135 | __Ceramic Tile | 0 hrs | 15 days | Thu 1/1/98 | Mon 1/12/98 | 0% |
| 136 | __Install Hardwood Floor | 0 hrs | 4 days | Wed 3/25/98 | Thu 3/26/98 | 0% |
| 137 | __Sand, Stain, Seal Hardwood | 0 hrs | 5 days | Mon 4/13/98 | Wed 4/15/98 | 0% |
| 138 | __Install Carpet | 0 hrs | 4 days | Tue 4/21/98 | Wed 4/22/98 | 0% |
| 139 | __Final Coat Hardwood | 0 hrs | 2 days | Wed 4/15/98 | Wed 4/15/98 | 0% |
| 140 | Paint | 0 hrs | 59 days | Tue 2/17/98 | Mon 3/30/98 | 0% |
| 141 | __Prep Drywall for Prime Coat | 0 hrs | 2 days | Tue 12/30/97 | Wed 12/31/97 | 0% |
| 142 | __Prime Paint Drywall | 0 hrs | 2 days | Wed 12/31/97 | Thu 1/1/98 | 0% |
| 143 | __Prep Trim for Prime Coat | 0 hrs | 2 days | Tue 1/20/98 | Tue 1/20/98 | 0% |
| 144 | __Prime Trim | 0 hrs | 2 days | Thu 1/22/98 | Thu 1/22/98 | 0% |
| 145 | __Finish Coat Trim | 0 hrs | 10 days | Mon 2/16/98 | Fri 2/20/98 | 0% |
| 146 | __Finish Coat Drywall | 0 hrs | 14 days | Thu 2/26/98 | Fri 3/6/98 | 0% |
| 147 | __Caulk Exterior Windows & Doors | 0 hrs | 1 day | Thu 3/26/98 | Thu 3/26/98 | 0% |
| 148 | __Finish Coat Exterior Trim & Siding | 0 hrs | 1 day | Fri 3/27/98 | Fri 3/27/98 | 0% |
| 149 | Draw #7 (Roofing, masonry, siding) | 0 hrs | 0 days | Tue 3/31/98 | Tue 3/31/98 | 0% |
| 150 | Interior Trim | 0 hrs | 29 days | Mon 6/15/98 | Fri 7/3/98 | 0% |
| 151 | __Interior Trim Delivery | 0 hrs | 1 day | Tue 1/6/98 | Tue 1/6/98 | 0% |
| 152 | __Install Interior Doors | 0 hrs | 5 days | Wed 1/7/98 | Fri 1/9/98 | 0% |
| 153 | __Install Interior Trim | 0 hrs | 15 days | Fri 1/9/98 | Tue 1/20/98 | 0% |
| 154 | __Install Cabinetry | 0 hrs | 5 days | Fri 2/6/98 | Tue 2/10/98 | 0% |
| 155 | __Install Appliances | 0 hrs | 1 day | Thu 2/12/98 | Thu 2/12/98 | 0% |
| 156 | __1st Punch-out Interior Trim | 0 hrs | 2 days | Fri 2/13/98 | Fri 2/13/98 | 0% |
| 157 | H.V.A.C. Trim | 0 hrs | 1 day | Mon 3/30/98 | Mon 3/30/98 | 0% |
| 158 | __Install Grills & Registers for Paint | 0 hrs | 1 day | Mon 3/30/98 | Mon 3/30/98 | 0% |
| 159 | __Set Outdoor Units | 0 hrs | 1 day | Mon 3/30/98 | Mon 3/30/98 | 0% |
| 160 | Plumbing Trim | 0 hrs | 5 days | Fri 4/3/98 | Tue 4/7/98 | 0% |
| 161 | __Set Fixtures | 0 hrs | 4 days | Tue 3/31/98 | Wed 4/1/98 | 0% |
| 162 | __Connect Appliances | 0 hrs | 1 day | Tue 4/7/98 | Tue 4/7/98 | 0% |
| 163 | County Final Plumbing Inspection | 0 hrs | 0 days | Wed 4/8/98 | Wed 4/8/98 | 0% |
| 164 | Exterior Landscaping | 0 hrs | 32 days | Mon 6/15/98 | Mon 7/6/98 | 0% |
| 165 | __Rough Final Grade | 0 hrs | 1 day | Wed 1/7/98 | Wed 1/7/98 | 0% |
| 166 | __Patios | 0 hrs | 7 days | Wed 1/7/98 | Mon 1/12/98 | 0% |
| 167 | __Porches | 0 hrs | 5 days | Mon 1/19/98 | Wed 1/21/98 | 0% |
| 168 | __Sidewalks | 0 hrs | 7 days | Fri 1/23/98 | Wed 1/28/98 | 0% |
| 169 | __Decks | 0 hrs | 7 days | Tue 2/3/98 | Fri 2/6/98 | 0% |
| 170 | __Driveways | 0 hrs | 2 days | Tue 2/17/98 | Tue 2/17/98 | 0% |
| 171 | __Final Grade and Seed | 0 hrs | 3 days | Wed 2/18/98 | Thu 2/19/98 | 0% |
| 172 | Electrical Final Trim | 0 hrs | 160 days | Mon 6/15/98 | Fri 10/2/98 | 0% |
| 173 | __Switch & Plug | 0 hrs | 2 days | Mon 1/12/98 | Mon 1/12/98 | 0% |
| 174 | __Install Fixtures | 0 hrs | 1 day | Mon 6/15/98 | Mon 6/15/98 | 0% |
| 175 | __Connect Appliances | 0 hrs | 1 day | Mon 6/15/98 | Mon 6/15/98 | 0% |
| 176 | Hardware | 0 hrs | 12 days | Fri 4/3/98 | Fri 4/10/98 | 0% |
| 177 | __Door Hardware | 0 hrs | 2 days | Thu 3/26/98 | Thu 3/26/98 | 0% |
| 178 | __Bath Hardware | 0 hrs | 2 days | Mon 3/23/98 | Mon 3/23/98 | 0% |
| 179 | __Mirrors | 0 hrs | 5 days | Thu 3/26/98 | Mon 3/30/98 | 0% |
| 180 | __Shower Doors | 0 hrs | 10 days | Tue 3/24/98 | Mon 3/30/98 | 0% |
| 181 | Draw #8 (Prime paint, cabinets, doors) | 0 hrs | 0 days | Tue 2/17/98 | Tue 2/17/98 | 0% |
| 182 | Draw #9 (Trim, furnace, hrdwd, tile, rails) | 0 hrs | 0 days | Tue 2/17/98 | Tue 2/17/98 | 0% |
| 183 | Draw #10 (Plumbing & elec. trim, final paint) | 0 hrs | 0 days | Thu 3/26/98 | Thu 3/26/98 | 0% |
| 184 | Final Building Inspection | 0 hrs | 0 days | Thu 3/26/98 | Thu 3/26/98 | 0% |
| 185 | Use & Occupancy Certificate | 0 hrs | 0 days | Mon 3/30/98 | Mon 3/30/98 | 0% |
| 186 | First Walk-thru | 0 hrs | 0 days | Mon 3/30/98 | Mon 3/30/98 | 0% |
| 187 | Draw #11 (Final payment per contract) | 0 hrs | 0 days | Tue 3/31/98 | Tue 3/31/98 | 0% |
| 188 | Final Punch-out | 0 hrs | 9 days | Mon 4/6/98 | Fri 4/10/98 | 0% |
| 189 | __Punch Out Walk-thru List | 0 hrs | 4 days | Mon 3/30/98 | Tue 3/31/98 | 0% |
| 190 | __Trim and Adjust Doors | 0 hrs | 2 days | Mon 4/6/98 | Mon 4/6/98 | 0% |
| 191 | __Paint Touch-up | 0 hrs | 3 days | Tue 4/7/98 | Wed 4/8/98 | 0% |
| 192 | Cleaning | 0 hrs | 14 days | Thu 4/2/98 | Mon 4/13/98 | 0% |
| 193 | __Windows | 0 hrs | 3 days | Wed 3/25/98 | Thu 3/26/98 | 0% |
| 194 | __Rough Clean | 0 hrs | 3 days | Mon 3/30/98 | Tue 3/31/98 | 0% |
| 195 | __Final Clean | 0 hrs | 2 days | Mon 4/13/98 | Mon 4/13/98 | 0% |
| 196 | Final Walk-through | 0 hrs | 0 days | Mon 4/13/98 | Mon 4/13/98 | 0% |
| 197 | Move-in | 0 hrs | 0 days | Thu 4/16/98 | Thu 4/16/98 | 0% |